Louisiana Integrated Resource Plan – 2027 filings
Entergy Louisiana’s Proposed Schedule of Events
| Filing initiating Fourth Full Cycle | October 22, 2025 |
| Begin survey of Stakeholders | November 21, 2025 |
| Complete survey of Stakeholders | December 22, 2025 |
| File Data Assumptions and description of studies to be performed | January 21, 2026 |
| First Stakeholder meeting | February 24, 2026 |
| Stakeholder written comments due | April 24, 2026 |
| Publish draft IRP report | October 22, 2026 |
| Second Stakeholder meeting | November 20, 2026 |
| Stakeholder comments on draft IRP report due | January 22, 2027 |
| Staff comments on draft IRP report due | February 22, 2027 |
| Final IRP report due | May 21, 2027 |
| Stakeholder list of disputed issues and alternative recommendations due | July 22, 2027 |
| Staff recommendation to Commission on whether a proceeding is necessary to resolve issues | August 23, 2027 |
| Commission order acknowledging IRP or setting procedural schedule for disputed issues | October 22, 2027 |
| Filing initiating Fifth Full Cycle | October 22, 2029 |
Entergy Louisiana 2027 IRP Filings
- Filing to Initiate 4th IRP Cycle (October 22, 2025)
As part of its fourth IRP cycle, Entergy Louisiana will supplement the typical IRP timeline by conducting a survey to gather stakeholder input prior to the company’s filing of Data Assumptions milestone.