Louisiana is growing. So we’re investing in the power grid to fuel that growth and meet tomorrow’s needs with clean, reliable and affordable energy. Take a look at some of our projects below, including more efficient, state-of-the-art power stations and new transmission lines that will increase reliability and withstand winds of up to 150 mph. For more detailed information on certain projects, click the links below.



Capital region

Capital Region Solar Project

  • 50 MW solar facility consisting of approximately 197,000 solar panels
  • Location: West Baton Rouge Parish
  • Completed: October 2020
  • Projected to bring approximately $6.4 million in tax revenue to the region over the next 30 years
  • Learn more information

Coastal Parishes

Ninemile West Bank transmission project

  • A three-phase technological upgrade of the transmission system on the West Bank of Jefferson Parish. The project will enhance reliability, increase transmission capacity and help ensure the availability of affordable power now and into the future.
  • Cost: $69 million
  • Completed: April 2019
  • Learn more information

St. Bernard reliability project

  • Construction of a new 230kV substation and two miles of transmission lines as well as upgrades to three existing substations
  • Location: St. Bernard Parish
  • Completed: June 2023
  • Learn more information

Terrebonne to Bayou Vista 230 kV transmission line project

  • A joint project between Entergy Louisiana and Cleco to improve reliability in southeast Louisiana. The 36-mile line will stretch from Gray to Patterson on steel structures designed to withstand winds of up to 150 mph.
  • Cost: $113 million (both Entergy Louisiana and Cleco)
  • Completed: Fall 2018
  • Learn more information

Greater New Orleans region

Harahan to Avondale transmission project

  • 230kV transmission river crossing built to withstand winds of up to 175 mph
  • Location: Jefferson Parish
  • Completed: August 2022
  • Learn more information

J. Wayne Leonard Power Station

  • 980 MW natural gas-fired combined cycle unit
  • Location: Montz, La.
  • Cost: $869 million
  • Completed: May 2019
  • Projected to save customers approximately $1.3 billion
  • Learn more information

Lake Charles Power Station

  • 994 MW natural gas-fired combined cycle unit
  • Location: Westlake, La.
  • Cost: $872 million
  • Completed: March 2020
  • Projected to save customers between $1.2 billion to $2 billion
  • Learn more information

Lake Charles transmission project

  • Construction of two new substations, expansion of a third, and the addition of about 25 total miles of high-voltage, storm-hardened transmission lines to move power more reliably and efficiently in the fast-growing region.
  • Location: Calcasieu Parish
  • Cost: $187 million
  • Completed: 2018

Mud Lake to Big Lake transmission project

  • 15 miles of transmission lines upgraded along with construction of a new substation and improvements to three existing substations
  • Location: Calcasieu Parish
  • Completed: August 2023
  • Learn more information

Southwest Louisiana infrastructure upgrade

  • A $100 million upgrade to the electric transmission infrastructure of Jefferson Davis Parish to enhance reliability and help ensure the availability of affordable power to help grow the region’s economy.
  • Location: Jefferson Davis Parish
  • Completed: November 2019
  • Learn more information
Download the free Entergy app on the App Store. Download the free Entergy app on Google Play.

Your account

Quick links

Additional links

© 2025 Entergy Corporation. All rights reserved.